Riegler worked on finishing the remaining Phase 3 driveways, sidewalks, and yard restoration today (11/6). There are still areas that will be addressed by Duke Energy so there will be gaps in the sidewalk until addressed. Riegler has begun milling both the Rogers and Meadow Wood intersections and prepping Buttermilk for paving on Monday.

Please be aware that the entire stretch of Buttermilk from Rogers to Meadow Wood will be closed Monday, beginning around 8:00 am (workers will be present starting around 7:30). Paving will be split with flaggers at Sunglow so that one lane of access will be maintained. There may be some temporary interruptions when shifting between sections. Emergency access will be possible during working hours. Buttermilk should be open to traffic Monday night for egress from Thirs.